Website Project Report 20/10/05

20 October 2005

To: Council, InternetNZ

From: Jordan Carter, Research & Policy Officer

Website Project: Budget & Timeline

A) Executive Summary

  • The website project was divided into three phases.
  • Phase zero (the interim website) cost $5,000, completed May 2004.
  • The current phase ( phase one the new CMS driven website) is scheduled to be completed in mid November.
  • Total cost for phase one is $98,000, which is detailed in the financial summary attached as Appendix 1.
  • This cost represents 73% of the amount budgeted for 2004-2006.
  • This phase is approximately six months behind the original schedule. A detailed milestones list is attached as Appendix 2.
  • This year's budget shows an overspend because of timing (underspend in 2004/05 resulting in overspend in 2005/06)
  • This report recommends reviewing the web strategy to date, and scoping out in more detail phase two (see section E below) options for inclusion in the 2006/07 budget.

B) Introduction

The functional development of the website using Zope and Plone is largely complete having reached acceptance testing. A 30 days warrantee period began following the system acceptance on 13 October 2005.

The outstanding issues for the release of the site are council acceptance before public release, project budget status and funding for remaining work in 2005/06.

C) Council Acceptance before Public Release

As agreed by Executive Committee at its September meeting, once the primary content has been edited the site will be released internally to two rounds of quality assurance. Firstly, a subset of councillors (Michael Wallmannsberger, Chris Streatfield, Rodney Prescott and David Harris) has been nominated for initial User Acceptance Testing. Once any agreed changes are made, a release to the full council will follow. Only when the site is approved for general release will it be eligible to go live to the public.

The timeline for key steps before public release is as follows, with a minor change since that presented at the previous meeting:

Date

Milestone

September 12

Content cleaning started

October 21

Priority content cleaned

Council representatives UAT starts

October 28

Wider Council UAT starts

November 15

Public release

D) Project Budget Status

In the interests of financial clarity on the budget for the project, the table attached at Appendix 1 shows a full breakdown of the website revamp spending from the InternetNZ budget in the past two years.

The table highlights the fact that a significant proportion of the expenses to date have been in maintaining the existing interim site, and on matters other than the simple development of the new site.

Items are divided into four categories of expenditure:

  • Interim Site items in these sub-lines relate to the development of the interim site, currently published at http://internetnz.net.nz/
  • Microsite Development for the Pacific Internet Partnership website
  • CMS Site Development these sub-lines are the costs of the project of building the new, CMS-driven website
  • Website Content for writing new content, and scrubbing the content migrated from the interim website.

Website development costs are identified as a sub-line within the communications budget line. As it is only the communications line which is adopted by the members the sub-lines can be amended. It is proposed to reallocate the sub-lines as follows, to allow for the completion of phase one work:

Communications Budget

Business Plan

Proposed

Change

INZ website
AGM
Advertising
Annual report
Technical Services
Member Meetings/Consultation
Communications materials

  • $65,000
  • $7,500
  • $5,000
  • $10,000
  • $35,000
  • $30,000
  • $60,000
  • $98,000
  • $7,500
  • $5,000
  • $10,000
  • $35,000
  • $15,000
  • $47,000

+$33,000




-$15,000 -$17,000

TOTAL BUDGET

$212,500

$212,500

nil

E) Next Steps: Remaining Work in 2005/06

With the completion of phase one imminent, it is timely to revisit the original priorities set out in the web strategy and to make decisions about where to proceed next in developing our web presence. Doing so will allow Council to make 2006/07 budget decisions on the basis of good information, and will ensure that the web strategy is relevant to InternetNZ' s current needs.

This scoping exercise is estimated to cost $10,000 and consists of two areas of work:

a) $5,000 review of web strategy & online priorities

The web strategy in place now was developed two years ago. Given the changes in InternetNZ' s work since that time, it would be prudent to review where we are at with our online strategy, and decide where (and how far) to progress in future.

b) $5,000 pilot online groupware

To investigate and trial groupware, including an online calendar/diary function for the new site and for the use of the secretariat/Council/Committees.

This paper recommends that $10,000 be re-allocated in 2005/06, from within the communications budget line (Communications Materials sub-line see table on previous page), to allow this scoping work to go ahead.

F) Project Milestones to Date

Please see the attached Appendix 2 for a timeline for the website redevelopment project to date.

G) Recommendations

It is recommended:

  1. That this report be received.
  2. That, to allow the completion of phase one of the website project and to provide for a review of InternetNZ' s web strategy, the reallocation of funds within the communications sub-lines in the budget as outlined in sections d) and e) of this report be agreed.

Jordan Carter
Research & Policy Officer

Note: this report is based on an earlier report provided by Shane Middlemiss to the Executive Committee.

 

Appendix 1: Budget and Expenditure - InternetNZ Web Project

2004/05

2005/06

Actual

Budget

Variance

YTD

Forecast

Budget

Interim Site (in use now)

Vendor

507

0

Project Management

4674

0

Site Maintenance

6593

619

619

Sub-total

11774

 

 

619

619

 

Microsite Development

Pacific Internet Partnership

960

.

Sub-total

960

 

 

0

0

 

CMS Site Development

CMS Evaluation

6700

0

RFI Evaluation

5188

0

RFP Evaluation

2958

700

700

Vendor

33332

42032

Design

5000

5000

Accessibility Testing

300

Project Management

21543

29543

Technical QA

2000

Information Management / Metadata

980

3179

3179

Sub-total

15827

 

 

63753

82753

 

Website Content

Content Writing

1500

6000

Content Scrubbing

9000

Sub-total

 

 

 

1500

15000

 

 

Total - Expenditure

28560

70000

41440

65872

98372

65000


Total Project

Forecast

Budget

Variance

Interim Site (in use now)

Vendor

507

Project Management

4674

Site Maintenance

7212

Sub-total

12393

 

 

Microsite Development

Pacific Internet Partnership

960

Sub-total

960

 

 

CMS Site Development

CMS Evaluation

6700

RFI Evaluation

5188

RFP Evaluation

3658

Vendor

42032

Design

5000

Accessibility Testing

300

Project Management

29543

Technical QA

2000

Information Management / Metadata

4159

Sub-total

98580

 

 

Website Content

Content Writing

6000

Content Scrubbing

9000

Sub-total

15000

 

 

 

Total - Expenditure

126933

135000

8067

 

Appendix 2: Internet NZ Web Project Milestones and Highlights

October 2003

  • Web Strategy Outline developed

February 2004

  • Interim website designed
  • Metadata strategy developed

March 2004

  • Technical architecture reviewed

May 2004

  • Interim site released for Council comment

June 2004

  • Open source content management systems evaluation drafted

January 2005

  • RFI released

February 2005

  • Ten RFI responses received
  • Four vendors selected to present credentials

March 2005

  • RFP released to shortlist of three vendors

April 2005

  • CMS vendor selected
  • Specification and scoping completed
  • Contract signed

May 2005

  • Information architecture completed

June 2005

  • Content types set

July 2005

  • Homepage and template layout

August 2005

  • Revised website design completed
  • Inventory of old website content and metadata keywords completed
  • Content publishing workflow implemented

September 2005

  • Old website content moved into new system